Showing posts with label Aircraft Carrier. Show all posts
Showing posts with label Aircraft Carrier. Show all posts

Saturday, September 18, 2010

Guam strategic locale for carrier facility

by Nick Delgado from KUAM.com

Guam - While the Record of Decision anticipated to be released on Monday, the commander of the USS George Washington says Guam is a very strategic area to have an aircraft carrier berthing facility. The military plans to dredge Apra Harbor to accommodate a deep draft wharf for the berthing facility inline with the buildup and relocation of Marines from Okinawa to Guam.

Commanding Officer Captain David Lausman says that other vessels such as the Kittyhawk, the Midway and the Independence have all been to Guam before, and he feels this will only strengthen the relationship with the military in the area. He does admit that it is rare for a Navy ship to hit a port more than once a year.

"It is very beneficial to have that," he explained. "It gives us another area to operate, we have a long history of military relationships there, some of the ranges are good, the ability to work with other forces there are good and operating area around that is very beneficial, so it's a very good thing and we are looking forward to coming back to it."

The George Washington is currently part of the annual Operation Valiant Shield exercise.

Saturday, February 20, 2010

Bordallo addresses people of Guam

Bordallo addresses people of Guam

Posted: Feb 16, 2010 7:27 PM
Updated: Feb 17, 2010 9:05 AM

by Sabrina Salas Matanane

*Madeleine Bordallo's Congressional Address
http://www.house.gov/apps/list/press/gu00_bordallo/congressional_address.html

Guam - Serving her fourth term in office, Guam Delegate Madeleine Bordallo delivered her annual Congressional Report on issues she has been working on over the last year as well as projects she is currently working on or will work on in the future. Here is a summary of the issues she touched on in her address before the Guam Legislature Tuesday evening:

* Bordallo discussed the issue of War Reparations and how she is pushing for its inclusion in this year's National Defense Bill.
* She plans to request increase funding for Compact Impact
* She will assist DOE in getting help from USDOE to resolve its funding crisis

The biggest chunk of her address was dedicated to the military buildup and the Draft Environmental Impact Statement. Bordallo listed off six areas of concern:

1. The Navy's Plans to acquire more land for the buildup: Bordallo said she will challenge the Navy to conduct the buildup within its existing footprint

2. Proposed Firing Ranges in Pagat and Sasayan: Bordallo said she is opposed to eminent domain and will ask the navy to re-evaluate the use of Naval Magazine as well as training ranges in Tinian as an alternative.

3. Air Craft Carrier Berthing: Bordallo plans to challenge the Navy to identify other alternatives that will minimize coral damage and take advantage are Kilo or Delta Wharves.

4. Lack of Financial Commitment from the Federal Government to fund civilian infrastructure projects: Bordallo is calling on the Navy to address this issue in a serious manner.

5. Lack of comprehensive housing for guest workers and providing healthcare needs in a manner that does not further overwhelm the island's infrastructure and healthcare system.

6. Socio-Economic Impact: Bordallo said the DEIS portion must be completely re-written in order to truly address the socio-economic impacts of the buildup.

The Congresswoman, meanwhile, said she supports the Governor's efforts to extend the construction timeline for the buildup. She said that in her comments she will submit on the Draft EIS she will request the Navy to provide a more realistic timeline and adjust the EIS analysis to reflect a realistic construction phase of eight to ten years.

In closing Bordallo mentioned President Barack Obama's upcoming visit next month which will give him an opportunity to hear the island's concerns. She ended by thanking the people of Guam and also recognized the men and women from Guam who are currently serving in harm's way in the Middle East.

Bordallo challenges DEIS

Bordallo challenges DEIS

Wednesday, 17 February 2010 03:37
by Therese Hart | Variety News Staff

Congressional report lists flaws of the draft study

THE military buildup must be delayed, Congresswoman Madeleine Bordallo said last night, acknowledging that the draft environmental impact statement has serious deficiencies that need to be addressed.

In her congressional report to the people, Bordallo identified six areas of concern regarding the draft study, including and the Navy’s desire to acquire additional private and public lands.

“We will challenge the Navy to conduct the military buildup on their existing land. The Navy should better utilize its land and consider moving housing and some support facilities for the Marine aviation unit to Andersen Air Force Base,” Bordallo said.

Secondly, an area of concern is the proposed firing range at Pagat and Sasayan. “If private property owners choose not to lease or sell their land I will support them and oppose any effort by the Department of Defense to use eminent domain to acquire that land. I recognize the input of private landowners and the organization ‘We Are Guahan’ on this issue.

A third area of concern is the proposed alternative for an aircraft carrier transient berth in Apra Harbor. “The plans for the carrier berth in Apra Harbor will result in a significant loss of coral. I will challenge the Navy to identify other alternatives that will minimize coral damage and that will take advantage of currently dredged areas such as Kilo or Delta wharves among others. I thank Senator Guthertz for her input,” said the congresswoman.

Fourth, she noted the need for federal assistance for improving civilian infrastructure on Guam to support the military buildup.

“While the DEIS draft report recognizes the need to improve civilian infrastructure it does not provide a clear strategy that details how the federal government will assist Guam,” Bordallo said as she opposed the Navy’s plan to drill 22 new wells in the north “until an independent assessment is made about the capacity of the northern aquifer.”

The fifth area of concern is the lack of a comprehensive plan for the housing of guest workers and providing for their health care needs in a manner that does not further overwhelm Guam’s local infrastructure and health care system.

“Let me be clear about this issue – we must do all that we can to train our local workforce and hire them before we utilize guest workers. Any proposal to house guest workers outside the gates must address their impact on civilian infrastructure such as water, wastewater and power. We cannot allow guest worker housing off-base to cause the faucets to run dry or power outages in our homes.”

Socioeconomic

Finally, Bordallo said, the socioeconomic portion of the draft study must be completely rewritten “in order to truly address the socioeconomic impacts of the military buildup.”

She said she will encourage the Navy to work closely with the University of Guam, the Guam Community College and the Department of Chamorro Affairs to develop a better understanding of the cultural issues and to formulate a comprehensive plan to support programs which preserve and promote Chamorro culture and language and I thank Fuetsan Famaloan for this input.”

On the issue of war claims, Bordallo said that she has made significant progress and that “we are closer than ever to passing this bill and we will continue to build on our progress.”

Bordallo spoke strongly on Guam’s quest for self-determination saying that Guam must refocus on the process to achieve decolonization and improve its political status with the U.S.

Projects

Bordallo also said she was concerned about the one of the assumption in the draft impact report that all projects will be completed by 2014.

“It would not be an exaggeration to say that this draft EIS has done more harm than good. The DEIS has not accurately identified the impacts on Guam and it has exaggerated some impacts based on a false assumption that all projects will be completed by 2014,” said the congresswoman.

“This flawed assumption has drawn consequences and conclusions that are not sustainable and not supported by anyone. Nobody wants 80,000 additional people on Guam in 2014,” Bordallo said. “We will do everything that we can, federally and locally, to stop that from happening. As I said before, we have our foot on the brakes. I will not support appropriations and authorizations that will result in a construction pace that brings 80,000 people to Guam in 2014.”

Tuesday, February 16, 2010

Get your DEIS comments in!

Get your DEIS comments in!

Posted: Feb 14, 2010 2:22 PM
Updated: Feb 14, 2010 4:41 PM

by Michele Catahay

Guam - Island residents have until this Thursday to comment on the Draft Environmental Impact Statement for the Marines' relocation from Okinawa to Guam. Back in 2006 an agreement was signed between Japan and the United States to move a portion of the U.S. Marine Corps Station in Okinawa to Guam. The plan would essentially transform the island in the Western Pacific into a giant arm of the Department of Defense.

According to the DoD's DEIS, by 2014 the island is anticipated to see its population of roughly 150,000 people increase significantly to 230,000 at its peak. That's an increase of 80,000 people within four years. The EIS outlines alternatives to develops and construct facilities and infrastructure to support the move. It also evaluates the impact of a new deep draft wharf to support a transient nuclear powered aircraft carrier.

The EIS also explores the impact of plans by the Army to develop facilities and infrastructure to operate a missile defense system. This would include relocating approximately 600 military personnel and their 900 dependents to Guam. While the island has until this Thursday to comment, the Guam Boonie Stompers along with the We Are Guahan Coalition hosted a clean up in Pagat, which happens to be one of the areas proposed to build a firing range for training.

Guam Boonie Stompers president David Lotz said his organization, "has a petition drive to submit to the buildup DEIS to keep these trails open, and I feel that's important for the community and even for the military to work towards preserving the island's heritage...if you look at the Quadrennial Defense Review, it actually says it's going to transform the island into a military base and it has to be very seriously looked at. Who is really going to control the future of the island? Is it the military or the people of guam?"

Yona resident Ulysses Story says negative impacts outweigh the positive ones for the island, saying, "To me, I think its traffic and another thing is racism. I mean, people, I think Chamorro people like to preserve their culture and bringing in people that are trying to assimilate them but they don't want to so I think it'll cause some conflict on racism."

Chalan Pago resident Ida San Nicolas says she's in support of the buildup, saying the military has a strong ability to help boast the local economy. "My child is 16 and it is his generation that it affects. My son has confronted me about it, and he has some issues with it but for me, we should let them speak also not just us and just saying what we think. All the jobs are for them and that's what I like is to be able to have some jobs," said San Nicolas.

Mangilao resident Aphea Imperial says while there may be some environmental impacts noted in the DEIS, she says the buildup will provide more opportunities for the island community, noting, "There are a lot of opportunities for the community like there are going to be a lot of jobs but there are also bad sides to it like our ecosystems, and it's just going to be overpopulated and guam is so small and i think it's good. i see military people and they help out a lot."

Again, you have until this Thursday to comment on the Draft EIS. To view the voluminous document, log on to GuamBuildupEIS.us.

Friday, February 12, 2010

Guthertz: Carrier Should Use Kilo Warf Rather Than Dredge Coral

Guthertz: Carrier Should Use Kilo Warf Rather Than Dredge Coral

Tuesday, 09 February 2010

Guam - Rather than dredge 36 acres of coral in Apra Harbor, Senator Judi Guthertz is proposing that the Navy continue to use Kilo Warf for any visiting Aircraft Carriers, and then moor ammunition ships out in Apra Harbor.

Visiting carriers currently use Kilo Warf, located near the tip of Orote Point, near Gab Gab Beach, but its primary purpose is for loading and off-loading ammunition.

However, the military's Draft Environmental Impact Statement argues that a separate berthing is now needed because of plans to extend the stay of visiting aircraft carriers to a total of 63 days a year and that would interfere with the "munitions mission" of Kilo Wharf.

Read Guthertz's Coment Paper on Aircraft Carrier Berthing
http://www.pacificnewscenter.com/images/pdf/gutpap.pdf

But in a "Comment Paper on Aircraft Carrier Berthing", Guthertz counters that "the assertion that the situation will become too difficult is not proven. It merely comes down to a matter of having a scheduling challenge."

In a release, the Chairperson of the Legislature's Buildup Committee, argues that: “The solution is to moor the ammunition ship at one of the deep draft buoys in outer Apra Harbor, where the Maritime Pre-position Ships (MPS) moor, whenever there is an overlap in their schedules. "

Guthertz says “This location for the ammunition ship would only be needed for those days when the aircraft carrier is moored to Kilo Wharf. The aircraft carriers would still be able to visit Guam at an enhanced frequency and duration compared to now.”

The Senator says it would be "a 'win-win' soultion for both.

"The aircraft carriers would have more ship visit days in Guam as desired by the military, and the coral would remain untouched as desired by the civilians.”

Written by : News Release

Scrapped wharf plan cost Port $1.5 million

Scrapped wharf plan cost Port $1.5 million

By Steve Limtiaco • Pacific Daily News • February 9, 2010

A $1.5 million plan to help the Port Authority of Guam create a new "deep water" wharf in outer Apra Harbor has gone to waste because the wharf project was scrapped.

According to a fiscal 2009 financial audit, released yesterday by the Office of Public Accountability and prepared by Ernst & Young, the cost of the wharf plan was recorded as a loss because the project won't be implemented.

The port remains open to the idea of the wharf project, according to Port General Manager Glenn Leon Guerrero, but it was estimated to cost as much as $83 million to complete and port officials decided to spend money on other improvements instead. There were also environmental concerns related to the wharf project, he said yesterday.

"As we were evaluating the need for this project, we learned of the impending military buildup, which then forced the port to redirect our energies to ensuring the necessary upgrades were implemented to our terminal facility to meet the demands of our community and the military buildup," he said.

The port will make improvements according to its modernization plan, but a deep water wharf is not part of the plan, Leon Guerrero said.
Pre-buildup

The idea of creating a new wharf and storage space on more than 17 acres of dredged soil was explored before the military buildup was announced, as a way to allow more aircraft carriers and other large vessels to visit Guam.

In September 2002, the government of Guam received a $1.5 million grant award from the Economic Development Administration, U.S. Department of Commerce, to prepare an architectural and engineering design, and an environmental impact statement for a new deep wharf in outer Apra Harbor, according to Pacific Daily News files.

The federal share of the wharf design and environmental study was $1.3 million, and the port's share was $200,000, which came from port revenue, Leon Guerrero said. The wharf plan was done by TG Engineers, the same company that designed the new landfill, and the environmental study was done by the U.S. Army Corps of Engineers.

Military wharf

The military's preferred plan for visiting aircraft carriers, according to the draft Environmental Impact Statement for the buildup, is to create a new carrier wharf at inner Apra Harbor. The military's proposal would require widening an existing shipping channel and dredging the seabed to create a turning basin near the wharf.


The audit report released yesterday states the port currently is waiting for $99.7 million in federal grants and loans so it can start working on the $200 million in planned improvements that are part of the modernization plan.

According to the audit, the port collected about the same amount of revenue during fiscal 2009 as it did during fiscal 2008 -- $30.1 million in fiscal 2009, compared to $30.18 million the previous fiscal year.

The audit notes the port collected about $636,000 less in cargo handling and wharfage fees, but collected about $897,000 more for equipment and space rental.
The port also cut its operating expenses by $378,000 last fiscal year, the report states.

Snorkeling outing showcases Guam's habitat

Snorkeling outing showcases Guam's habitat

Posted: Feb 08, 2010 4:32 PM
Updated: Feb 08, 2010 6:31 PM

by Heather Hauswirth

Guam - Members of the We Are Guahan Coalition sponsored a four-hour snorkeling trip to outer Apra Harbor on Sunday so that residents could see for themselves the rare coral and fish whose habitat will be disrupted by proposed dredging cited in the Draft Environmental Impact Statement in order to accommodate a pier for an aircraft carrier.

While parts of Apra Harbor are open to the public, this may not be the case for long. On Sunday more than 100 snorkelers scoped out the habitat that thrives in jade and western shoals. We Are Guahan member and Southern High Social studies teacher Collin Smith says there's no doubt that the construction of an aircraft carrier pier will have dire consequences on the marine habitat.

"Some of the reef will actually be gone. Some of it will be gone directly taken out and that's it. Some of the reef will be killed when the sand spreads out in the water and impacts other areas. In the DEIS they say 39 acres will be directly impacted, but it's more like 70 acres will be directly impacted," he noted. "To give you a sense of the scale of this, 39 acres is 21 Micronesia Malls."

While the DEIS states that existing fish stocks can easily relocate to another habitat, marine biologists say otherwise. They argue that removing any coral especially older colonies - permanently reduces the number of surrounding fish.

Legislative Speaker Judi Won Pat, who saw some of the 110 different species of coral herself during the dive, won't allow dredging in Apra Harbor without a fight. "It was an experience I've never had diving or snorkeling here. The large coral heads I'm sure took so many years to grow to that size. There are a lot of fish down there, so it is a habitat for our marine life so I surely don't want to see anything like that disturbed," she said.

For research psychologist and University of Guam professor Mike Elhart, he questions whether or not alternatives are even possible. "Should it not happen? Do we not need to be careful with defense? Of course we do, but the question is can they do it some other way. Could they, for example, set it up further out in the port, another part of the port where it wouldn't damage as much reef that's public access? I don't know the solution, but dredging deeper areas here doesn't seem to be a reasonable way to do it," he said.

Guthertz drafts strategy for coral dredging

Guthertz drafts strategy for coral dredging

Posted: Feb 08, 2010 2:15 PM
Updated: Feb 08, 2010 2:15 PM

by Nick Delgado

Guam - Senator Judi Guthertz has proposed a solution to concerns raised about the dredging of 36 acres of coral in Apra Harbor to accommodate an aircraft carrier berthing. The Democrat lawmaker has suggested that ammunition ships be moored at one of the deep draft buoys in outer Apra Harbor where maritime pre-position ships moor.

Guthertz stresses that because an aircraft carrier is not expected to spend more than 63 days a year on the island, using kilo wharf would be a better solution. "If there's an overlap between the ammunition ships that use Kilo Wharf and the carrier, then they need to take turns. Either the ammunition ships can be out in the water and stay while the carrier comes in and vise-versa," said the senator.

Thursday, February 11, 2010

Compromise deal on carrier berthing problems proposed

Compromise deal on carrier berthing problems proposed

Monday, 08 February 2010 04:25
by Therese Hart | Variety News Staff

NOTING the community’s concern over the aircraft carrier berthing plan, Sen. Judi Guthertz said the solution is to moor the ammunition ship at one of the deep draft buoys in outer Apra Harbor where the Maritime preposition ships moor, whenever there is an overlap in their schedules in Kilo Wharf.

In a detailed comment paper submitted to the Joint Guam Program Office, Guthertz said this alternative was not studied in the draft environmental impact statement.

“The DEIS states that the current scheduling overlaps are manageable, but fears that with enhanced carrier port visits and increased ammunition ship visits that the situation will become more difficult. I assert that this cannot be proven,” said Guthertz, chair of the committee on the Guam military buildup and homeland security.

Guthertz said her suggestion is a “feasible fall back option to the DEIS’ preferred option,” which is to use Apra Harbor.

The location for the ammunition ship would only be needed for those days when the air craft carrier is moored to Kilo Wharf, she said.

The air craft carriers would still be able to visit Guam at an “enhanced frequency and duration compared to now,” said the lawmaker.

No dredging of coral will be required, said Guthertz. Extensive dredging has been done around Kilo Wharf, primarily to clear rock and coral under and next to the extension itself.

The draft study proposes the dredging of about 36 acres of coral in Apra Harbor to accommodate a new pier for berthing nuclear aircraft carriers.

The impact report claims that if aircraft carrier visits are extended to total 63 visit days a year, that the munitions mission will suffer if the current Kilo Wharf is continued to be used for the aircraft carriers.

Kilo Wharf, located near the tip of Orote Point, near Gab Gab Beach, is currently used for aircraft carrier visits while its primary purpose is to moor ammunition ships, said Guthertz.

Guthertz’s paper states that the assertion that the situation will become too difficult is not proven. It’s a matter of having a scheduling challenge.

Guthertz asserts that the draft study’s position to destroy 36 acres of coral reflects a viewpoint of maximizing the satisfaction of the military needs.

“I believe that a firestorm within the civilian community has begun over the coral destruction issue,” she said. “A compromise is needed that provides for the core-interests of both sides being protected. My solution does that.”

Thursday, January 07, 2010

First buildup hearing held in South

First buildup hearing held in South

Posted: Jan 08, 2010 12:10 AM
by Nick Delgado

GUAM - The first public hearing on the Draft Environmental Impact Statement was held Thursday evening at Southern High School in Santa Rita. Approximately 319 island residents participated, some to listen to proposed plans, while others provided comment on the marine relocation from Okinawa to Guam.

Joint Guam Program Office Chief of Staff colonel Paul Pohn presented the military's proposed actions for the buildup. Those proposals include developing and constructing facilities and infrastructure to support approximately 8,600 marines and their 9,000 dependents, a new deep-draft wharf and turning basin along with shore side infrastructure improvements to be constructed at Apra Harbor to support U.S. Navy transient nuclear aircraft carriers, and finally develop facilities and infrastructure to support relocating 600 military personnel and their 900 dependents to establish and operate an army air and missile defense task force.

Residents were informed that the hearing would only allow for them to submit comments, and not debate their concerns with military officials. While the population increase is dependent upon the funding available to begin the buildup, Pohn says the military's goal is to use as much DOD land as possible, as he says it's still too soon to determine what land is needed at this time.

Al San Agustin with the Chamoru tribe expressed how the military buildup would not be a good thing for the people of Guam, as it will negatively impact the future generations. Tribal chairman Frank Schacher says he has been carefully studying the draft EIS Schacher claims there is not one bit of information that shares the impacts of the Chamorro people. He adds that the DEIS consists more of the questions that the military wants answered rather than what the people of Guam want.

Chamber of Commerce President David Leddy meanwhile expressed why the island needs the military's presence to help better Guam's economy.

Concerned resident Kenneth Leon guerrero shared his frustration with the lack of public safety information in the DEIS. Leon Guerrero questioned the lack of statistics that show the crime rate that the marines have committed off base in Okinawa, and how the military plans to mitigate the issue on Guam.

While local veteran Tom Barcinas stated that Guam and America need each other, he also said it is very sad to think that the Chamorro people will become the minority. Barcinas says the impact will compromise the island's culture, value, and language, which he says is a very high price to pay.

Resident Angel Santos questioned why Guam is the only place being selected over the other areas in the region. He fears that Guam will be more of an easy target with the increase in military.

Former Chamoru nations maga'haga Trini Torres says that it is not a done deal as she is determined to continue the fight to prevent the marine relocation. Torres expressed major frustration encouraging others to do the same.

Piti Mayor Ben Gumataotao however stated that the military is not coming to bring war to the island, but to help the economy and defend the island for everyone living on it.

Residents were also given a summary explanation of the DEIS. At each station during the open house period. JGPO officials say all comments will now be included in volume 10 of the DEIS.

Residents have another opportunity to provide oral comment this Saturday at the University of Guam Field House in Mangilao. The public also has until February 17th to comment on the DEIS by logging onto www.guambuildupeis.us

Friday, December 04, 2009

Is price tag for carrier wharf worth it?

Is price tag for carrier wharf worth it?

Posted: Dec 03, 2009 2:54 PM
Updated: Dec 03, 2009 6:53 PM

by Heather Hauswirth

GUAM - In the name of national security, the environment will likely take a back seat if JGPO green lights its plans to construct a pier, called a berthing, for a nuclear transient aircraft carrier in either Apra harbor or the ship repair facility located on Big Navy.

You've heard it time and time again, Guam is the tip of the spear. The draft EIS revealed by the Joint Guam Program Office just two weeks ago includes the hypothetical blueprint for the way millions of dollars in construction projects could be spent on land and on sea. The ranking Naval Officer for naval facilities, captain Scott Galbreaith says the navy would like a greater air craft carrier presence on U.S. soil.

"It's a very potable and potent striking force and engagement force for the U.S. Being out here – forward deployed in the Western Pacific where the aircraft carriers often operate. This transient pier would give them flexibility in having a place to come and do maintenance and a little bit more training."

What is to become of the habitat with increased sedimentation, and permanent damage to the coral reefs?

Shawn Wusstig co–leads the Guam sea turtle recovery program for the Department of Agriculture.

According to Wusstig, "Here on Guam one of the greatest threats we have to sea turtles both hawksbill and green is habitat loss. What was once suitable for nesting may no longer be suitable and that would also depend on what type of best management practices that are in place that will keep that shore in tact."

Yet Captain Galbreaith says the threats from the neighboring Philippine sea, the People's Republic of China, and North Korea all make it necessary for the U.S. to establish an aircraft carrier pier in the Pacific.

"It is a floating air station really and it carries about 70 aircraft many of them capable of performing strike missions, refueling airborne, early warning and helicopter asw and other multi–mission capabilities," Galbreaith elaborates.

The Guam Shipyard and Polaris Point are the two proposed locations for an aircraft carrier pier. This would provide the Navy with a third location for an aircraft carrier pier in addition to the ones that exist in Hawaii and Japan.

Building this wharf requires

• up to 1,325 ft in length

• deck height of + 12 ft

• pier strength: 800 lbs per sq. Ft.

• mobile crane load: 2,140 ton

"The nuclear carriers are deeper than Kitty Hawk so in the past when we brought in nuclear carriers they had gone to our kilo wharf out by Orote Point, but that is really a wharf meant for ammunition movement so whenever we brought a carrier in that meant we couldn't do our job of ammunition movement so we want a dedicated wharf for the carrier," Galbreaith explains.

although not yet factored into the military budget for this next fiscal year, Captain Galbreaith says it is likely to be included in Fiscal Year 2012 at which time it will be up to Congress to approve or amend this project.

Carrier berthing carries huge costs

Wednesday, December 02, 2009

Sifting through the Draft EIS

Sifting through the Draft EIS

Posted: Dec 01, 2009 10:04 PM PST
by John Davis

Guam - As I continue to read and review the Draft Environmental Impact Statement, I continue to find unclear language that is a cause for concern. Today, let's talk about the DEIS VOLUME 4. Volume 4 explains the need, purpose and impacts of constructing a deep-draft wharf to support an aircraft carrier and Carrier Strike Group.

The purpose and need for the deep-draft wharf is to allow the Navy the ability to locate military forces to meet international agreements and treaty requirements to fulfill U.S. National security requirements to provide mutual defense, deter aggression and dissuade coercion in the Western pacific Region. Satisfying those requirements also include positioning forces to defend the homeland, including U.S. Territories and provide a location with a timely response range. This is probably why Guam is referred to by the Federal Government as the "Tip of the spear." However; I have a different opinion to why our island is referred to as the U.S. Military's Tip of the spear in the region. For example, if the Department of defense were as business and it was looking to branch out in our region, despite the fact they have satellite offices (military bases) all over the globe, Guam would be the best location to engage, show presence and deter aggression in the western pacific region.

With the prime location for the increase in U.S. Military presence already determined, let's focus on more DEIS language that raises more cause for concern. Allowing visiting and transient aircraft carriers and carrier strike groups to move freely through Guam and international waters throughout the region attempts to maintain regional stability, peace and security. Another goal of being able to support aircraft carriers and CSG's is to provide a powerful U.S. presence within the Western Pacific Region. Will the military only focus on beefing up the Western Pacific region? If the U.S. Military will only focus on increasing strength in the western pacific region with a population of billions of people, what about the millions of people living in the Atlantic Region?

According to DOD, the global perspective is to have aircraft carriers deployed world wide to support U.S. interests and commitments. On the other hand, I say DOD's DEIS is full of non-commitment. We have not received any guarantees related to cost sharing measures to fund the military buildup. In fact, the only commitment Guam has received from the U.S. military is that there will be 8 thousand Marines and about 72 thousand other support personnel on Guam by 2014. What OTHER U.S. interest requires a deep-berthing wharf for an aircraft carrier and strike group other than the war on terror? Is Guam under threat from China, North Korea, Russia, Malaysia or the Republic of the Philippines? I'm sure our people would like to know what kind of ride they're in for.

Furthermore, the DEIS states the employment of a CSG is integral to supporting U.S. interests and meeting treaty and alliance requirements globally and nationally. More gray area if you ask me. What the DEIS doesn't spell out is whether or not there is a risk for the U.S. to be in violation of a particular treaty? What about an alliance internationally or is the U.S. at risk of violating national interests? If not, why not build up Puerto Rico, the Virgin Islands or American Samoa? With respect to global interests, why not have this buildup somewhere else around the globe, why does it have to be Guam? Is it because we as a people have not determined our political status? I think so, but it would be nice if the DOD admitted it.

After the construction of a deep-berthing wharf, the DEIS indicates the Aircraft Carriers mission will be to provide credible, sustainable, independent presence and conventional deterrence during peace time. What I would like the DOD to indicate is whether or not the Western Pacific Region is at peace now. There are several ongoing conflicts ongoing right now in the Western Pacific Region and other regions around the world. According to information in the DEIS the aircraft carriers mission is to provide a sustainable, credible presence. Are there any projections to this buildup ever being downsized? That would be nice to know too. Aircraft carriers and CSG's will operate as the cornerstone of JOINT/ALLIED maritime expeditionary forces in times of crisis. A time of crisis would be now considering the ongoing war on terror. If the aircraft carriers will serve as the cornerstone of JOINT/ALLIED expeditionary forces, what role will Guam play other than playing host to the U.S. war machine on our native lands?

Aircraft carriers and CSG's will launch and support attacks on enemies, protect friendly forces and engage in sustained independent operations of war. Who exactly are the "enemies" and what are independent operations of war?

When all is said and done, after all the construction and migration of U.S. military forces to Guam, the navy plans to adjust its force posture and basing to position at least 6 operationally sustainable carriers and 60 percent of its submarines in the pacific to support engagement, presence and deterrence. I understand these 6 carriers will be able to move around the Western pacific region, pulling in and out of port whenever they please, but can DOD or the navy confirm whether or not at least one aircraft carrier and CSG will call Guam its home port? If so, then I'm looking forward to an increase in Section 30 Revenues. On the other hand, aircraft carriers are deemed a sovereign U.S. Territory, which is why I think this is a potential out for DOD not to increase section 30 funding to GovGuam. I would also like to know if any nuclear submarines will call Guam their home port as well. If this is true, then how will the Navy or DOD ensure there isn't another radioactive material leak?

When the DOD says "support engagement, presence and deterrence, it that the order of priority? Does the DOD plan to engage enemies before showing presence and deterring engagement? I would like to think the humanitarian way would be to first show presence, second deter and third and lastly engagement.

Not to worry readers, I'm not quite done reviewing the 400 pages of volume 4, if you've read volume 4 or any other part of the DEIS, chime in, I'd like to read your comments.

Saturday, November 28, 2009

Increased sedimentation threatens ecosystem

Increased sedimentation threatens ecosystem

Posted: Nov 28, 2009 1:36 PM Updated: Nov 28, 2009 5:04 PM

by Heather Hauswirth

Constructing a berthing for a nuclear transient aircraft carrier pier slated for either Apra Harbor or the shipping repair facility near Polaris Point does not come without significant environmental consequences. Dredging and other construction related activities increases sedimentation levels in the water.

Manny Duenas said, "Apra Harbor is a major lagoon for Guam and lagoons are normally good places for breeding grounds for fish and marine life and with the sediment that will be coming from Apra Harbor, I don't know how you can mitigate fine particles and the turbidity issue. It will affect Guam in itself because we know the fish don't just live in one area." The Fisherman's Co-Op president said biologists agree that the most acceptable paradigm for the natural environment is one where sedimentation is kept to a minimum.

Guam EPA Environmental Monitoring and Analytical Services Administrator Jesse Cruz says it is disruptive to the overall marine environment, saying, "During the dredging process, the sedimentation that could result from dredging has an impact on mainly the corals and the coral reef area where the fine sediments that will be released during the dredging process could be distributed through the larger area with the currents and settle down on top of the coral, which could cause a smothering affect of the corals."

A smothering of the corals would diminish their survivor ship in the area as sedimentation shades out the sunlight, which corals need for survival. Despite strict protocol in place for dredging, the Joint Guam Program Office's asst environmental director on Guam, Randel Sablan says there is no way to avoid it, but there may be a way to mitigate the impact.

He said, "On the compensatory side - what do we do with the coral that were impacted? Well, the army corps permit that the navy needs to obtain in order to do the dredging will require compensatory mitigation and in the DEIS there are four types of compensatory mitigation proposed."

These options include building an artificial reef to replace the services and functions lost, doing water shed enhancements to reduce erosion that impacts coral reefs, coastal mitigation proposals such as increasing waste water treatment, and a mitigation banking program where the Navy would outsource mitigation projects to a third-party.

But Cruz pointed out that isolating construction and dredging as much as possible is actually what's key to mitigation, saying, "Silk curtains or silk screens during the operations to minimize the fines from the area of the dredging, keep the dredging area to as minimal space as possible."

The debate continues about the best way to approach mitigation. As time goes on, fishermen like Duenas say they won't pipe down as long as there are fish that are going to be impacted by dirtier water. "Any fish in Apra Harbor part of the reproductive stage or part of the replenishing of this islands resource that will be removed," he said.

Duenas continued, "I saw the map for dredging of Apra Harbor and they are going to come right down the middle. That is a whole reef area that they are going to impact.

"And that's really sad."

Tuesday, November 24, 2009

New wharf project

New wharf project

Tuesday, 24 November 2009 02:48
by Jennifer Naylor Gesick and Jude Lizama |
Variety News Staff

Polaris Point identified as site for aircraft carriers

THE Navy has determined that Polaris Point is an ideal location for building a port capable of hosting visiting aircraft carriers. It is preferred over utilization of the former ship repair facility at Apra Harbor, according to the draft environmental impact statement.

Increased carrier operations in the Western Pacific and Indian Oceans mean aircraft carriers could visit Guam 63 days a year. With carrier crew capacity of nearly 6,000 men and women, port of call visits pump millions of dollars into the local economy as crew members can spend upwards of $200 to $300 a day on rental cars, hotel rooms, at restaurants and local shops.

Kilo Wharf has been used in the past, but as the military realignment progresses, but visits by carriers longer than a week would disrupt existing munitions operations at that wharf necessitating a more suitable location for the nuclear-powered floating airfields which need almost 50 feet of depth to safely come into port.

Ship ahoy

Other requirements planners are looking out for include shoreside infrastructure improvements at a new wharf to include utilities such as power, wastewater management, and potable water supply to minimize and eliminate dependency on shipboard systems while in port.

The draft impact statement further detailed the potential need for such facilities as laundry, recreation, transportation support for shuttle services and food and beverage concessions.

Polaris Point is expected to see a considerable increase in daily activities when aircraft carriers are in port with people transiting the wharf area, more truck traffic from the Navy base and vendors servicing visiting ships.

Cargo movement, the Navy anticipates, will likely require mobile cranes and other materials-handling equipment such as forklifts.

This aspect has raised some eyebrows among local leaders with Sen. Ben Pangelinan already having questioned the implications of the Navy diverting cargo to their facilities and avoiding the Port of Guam.

Digging in

About 1.1 million cubic yards of dredged material will be excavated from the Inner and Outer Apra Harbor for the proposed Navy and Marine Corps actions.

To reach the depth requirement dredging of the area will have to be done, and there are two methods, mechanical and hydraulic. The impact statement details mechanical dredging, which has historically been used in Apra Harbor, as the most likely way to prepare for a deeper water line at Polaris.

Mechanical dredging uses a bucket and hydraulic uses pipes and pumps to excavate the material. However, the methodology is controversial among some locals and with some environmentalist as well.

The draft study recognizes that mechanical dredging has the greater combined potential for environmental impacts, directly and indirectly, due to sediment redistribution which could destroy the areas valuable coral reefs.

The report additionally cited a need to develop temporary solid and hazardous waste storage areas at a proposed new wharf as well as a building to house on-site port operations for storage and other administrative purposes when a carrier is not in port.

Ecological crisis

Increased land needs are expected to have a critical impact on the environment as soil compaction and erosion, runoff, soil and subsurface contamination are cautioned against in the report. The U.S. government currently holds nearly one-third of all Guam lands under its aegis.

Buildup activities could further contribute to an ecological crisis on Guam if proper planning does not account for cut-and-fill activities, removal of vegetation and landscaping and the proper use of heavy equipment on projects, according to the study.

The long-term implications of what has been described as the largest military realignment in U.S. history is based upon information included in the report which purportedly studied environmental consequences of ground combat training, air combat and logistics combat training and support as well as the affect of encampment areas, training airfield and waterfront functions.

Vehicle and troop movements, munitions impacts, and explosive detonations were also considered in the report.

While there are proposed alternatives for the main encampment areas, training-firing range, training-ammunition storage, and training-Naval Munitions Site access road initiatives, there are no airfield or waterfront initiative alternatives.

Hazardous waste

Geological and soils impacts were conducted, in part, by reviewing documentation like previously published National Environmental Policy Act documents for actions in the Mariana Islands Range Complex and surrounding areas.

It is estimated that the proposed transfer of Marines to the island will result in an annual hazardous materials disposal volume of approximately 16,000 lbs.

The projected increase in hazardous waste may create adverse impacts to the environment and human health; however, the study states that best management practices and standard operating procedures will be utilized to ensure that no significant impacts occur.

The study also cited that such increases in the use and transfer of hazardous materials may require local Defense Reuse and Marketing Offices to expand “hazardous materials handling, storage, and disposal capacity.”

Projects cited as having potential impacts on local soil and geology resources include the construction and operation activities at the Andersen Air Force Base , main cantonment construction and operation activities, waterfront and Naval Base improvements at Apra Harbor, range operations at Navy Barrigada and NMS, and training activities at Andersen South and Route 15 Parcel.

Monday, November 23, 2009

Military plans aircraft carrier in Apra Harbor

Military plans aircraft carrier in Apra Harbor

Posted: Nov 23, 2009 4:50 PM
by Heather Hauswirth

Construction of a deep draft wharf that would support a transient nuclear powered aircraft carrier in Apra Harbor, Guam requires over 5,600 military personnel alone to maintain daily operations - the carrier is the largest ship in the Navy's fleet.

The Draft Environmental Protection Statement describes why the Department of Defense wanted to construct an aircraft carrier on the island. Some of the reasons include that Naval Base Guam already possesses emergent nuclear repair, radiation response and radioactive waste management capabilities.

* The aircraft carrier is recognized as a floating sovereign U.S. territory
* The island's location in the Western Pacific is deemed vital for U.S. national security interests given threats from neighboring China, North Korea, and the Philippines

Aircraft carriers are deployed all over the world and used to support aircraft attacks during combat, provide deterrence during peacetime, and engage in independent operations of war during times of crisis. The projected annual carrier visits to Guam in the DEIS are estimated to be 63 days per year based on operational and geopolitical factors.

The Department of Defense identified Apra Harbor, an active commercial and military port, and Polaris Point, as the most suitable location for the aircraft carrier. The DEIS dismissed several nearby alternatives like Dry Dock Island, and the Commercial Port, shooting them down for unavoidable dredging in the Sasa Bay Preserve and the force protection costs associated with those locations seen as more vulnerable to attack from ships that might come in from the Phillipine Sea.

Other factors taken into consideration had to do with the cost of structural design requirements needed to shield wind and wave impacts and ecological concerns related to ensuring minimal damage occur from dredging, according to the DoD.

For instance, all aircraft carriers require 6-feet be beneath the keel to ensure a cooling system is not clogged or damaged by mud from the debris of the sea floor. Whether built in Apra Harbor or Polaris Point, the environmental impact on the coral reefs and habitat that will be disrupted is being considered.

The Department of Agriculture has taken the lead warning that the agency is looking closely at the DoD's analysis to ensure construction with minimal irreversible damage is done to the reef and existing habitat.